Environmental Education Grants Program Scope of Work Instructions
Project Period: July 1, 2025 through June 30, 2026
A. General Information
Complete the required information:
Legal Name of the applying Organization:
EE Grant Project Title:
Project End Date:
Project Director’s Name:
Project Director’s Email:
Project Director’s Phone Number:
B. Benchmarks
Use the rows to describe major Project tasks (benchmarks) to be completed.
- 1) Enter the benchmark tasks in chronological order;
- 2) Enter
a single Target Date of Completion (within the current grant round Project Period). Do not enter a span (such as January-March 2026). Spans should be inserted within the benchmark description (see F below); and
- 3) Assign one Activity Letter, in alphabetical order to each Benchmark.
Example:
Activity Letter |
Benchmarks (Insert rows, as needed) |
Target Date of Completion (month/year) |
A | Work with Partners to plan workshop. Secure facility for Community Workshop #1 and begin advertising | August 2025
|
B | Finalize agenda, purchase equipment and materials, and begin processing registrations | September 2025
|
C | Submit draft assessment tool for review and feedback | October 2025
|
D | Host Community Workshop #1 | November 2025
|
E | Submit Midterm Progress report (Workshop #1 benchmarks, assessment results, and supporting materials)
| January 15, 2026
|
F | Advertise Workshop #2. Secure transportation. Process registrations (January-March 2026)
| March 2026
|
G | Host Community Workshop #2 | April 2026
|
H | Present the Project at a local meeting, conference or other appropriate event to share project goals, “Lessons Learned”, etc. | May 2026
|
I | Submit Final report, assessment results and supporting materials | June 10, 2026
|
Note: Enter the applicable Scope of Work's benchmark Activity Letter(s) on the Detailed Budget Sheet tabs (People costs, Travel costs, Resource Costs, Other Costs and Budget Match).
Required Benchmarks
The following Benchmarks are
required and must be listed
individually and chronologically among the other major tasks (project benchmarks) to be completed:
1. Draft Assessment tool to be submitted for review and feedback
Enter Target Date of Completion as January 15, 2026
Note: Draft Assessment tools must be submitted
prior to engaging the audience(s). If the project will engage the audience between July-December, enter a month/day/year that is at least 4-6 weeks prior to interacting with the audience.
Example: A program is anticipated to be delivered to an audience by November 15, 2025. The draft assessment tool must be submitted for review and feedback no later than October 1, 2025.
2. Midterm Progress report
Enter Target Date of Completion as January 15, 2026.
3. Present the Project at a meeting, conference or other appropriate event to share project goals, “Lessons Learned,” accomplishments, etc.:
Enter Target Date of Completion as Month/Year.
Note: General Grants present at a regional, statewide, or other far-reaching events. Mini Grants may present at local venues.
4. Final Report, assessment results and supporting materials
Enter Target Date of Completion as Month/Day/year
Note: The Final Report must be submitted 14 business days after the project has concluded. The Target Date of Completion for projects concluding on June 30, 2026 is July 15, 2026.
C. Subcontractors
Complete the Subcontractors section:
Subcontractors |
List the name and FID# of all subcontractors to be utilized on this project. Subcontractors yet to be identified cannot begin work until required information is submitted to the DEP:
|
Name |
FID# |
Name of Contractor #1 |
Contractor #1 FID# |
Name of Contractor #2 |
Contractor #2 FID# |
Name of Contractor #3 |
Contractor #3 FID# |
If you have not identified the Subcontractor or do not know the FID#, the information must be provided to DEP prior to the Subcontractor beginning any work.
D. Budget
The
Scope of Work Budget numbers must be identicval to the numbers that appear on the
Grand Total tab of the Detailed Budget Sheet (excel document). Complete the Detailed Budget Sheet. Then enter the numbers that appear on the Grand Total tab in this section:
Budget |
Grant Funds: | $ Must Match Detailed Budget Grand Total |
Grant Share (Match): | $
Must Match Detailed Budget Grand Total |
Total Project Costs: | $
Must Match Detailed Budget Grand Total |
The DEP share shall not exceed the grant amount listed above.